Utility-Scale ESS In Czech Republic

Project Size
37.95MW/41.7MWh
Project Highlight
As the?largest utility-scale energy storage project?in the Czech Republic, this system is strategically located at the Czech–German border and directly connected to a high-voltage substation. It specializes in providing services for the European frequency regulation market, effectively maintaining grid stability and supporting the seamless integration of renewable energy across borders.

Get in Touch